There are many exciting developments to report in the transportation arena, as we complete work on the draft 2000-2004 Transportation Improvement Program and Long Range Transportation Plan. Due in part to the significant increase in federal transportation funding under the Transportation Equity Act for the 21st Century (TEA-21), MAG has developed and released a proposed acceleration schedule for the freeway system and other important projects. This accelerated schedule would result in completion of the Regional Freeway System by 2007 seven years earlier than planned.
The Regional Transportation System Plan is, however, based on a number of financing assumptions. Among these assumptions is that the state would be able to borrow up to $400 million dollars from itself through financing mechanisms such as the State Infrastructure Bank (SIB), the Highway Expansion and Extension Loan Program (HELP), or Grant Anticipation Notes (GANs).
These financing methods can not be utilized, however, unless state lawmakers first approve critical legislation. House Bill 2572, which would enable the state to borrow the money, is expected to pass in the House, but will likely face a stiff challenge in the Senate. We would strongly encourage cities to work very actively with lawmakers on this legislation, which would assist in delivering the accelerated freeway system to the voters in their districts.
We also continue to seek your support in opposing HB 2181,
which calls for the creation of an Urban Planning Division within
ADOT to develop a regional transportation plan. The intent of
the bill is to reassign many of the transportation planning functions
of MAG and give them to the state. As we have mentioned previously,
there are multiple problems with HB 2181 related to consistency
with federal regulations, involvement of local decision makers
in the transportation planning process, and creation of a process
which establishes another level of bureaucracy within ADOT to
duplicate work mandated to MAG. The legislation does not comply
with federal law and would jeopardize federal transportation funds
available to the region. I urge you to rigorously oppose this
bill.
There are also many items of interest to report on Census 2000
efforts. As the representative of the International City/County
Management Association on the U.S. Commerce Secretary Census 2000
Advisory Committee, I have had two recent opportunities to testify
before a Congressional Subcommittee on census issues important
to local governments. There are four major issues which warrant
attention: how to tabulate and report race choices; the Master
Address File update; statistical adjustments to actual counts;
and post-census local review. Here is a quick synopsis of the
issues and actions to date in each of those areas.

Proposed Project Acceleration Schedule Gets First Review in
Study Session
From the addition of HOV lanes on the Superstition, to eight grade-separate
interchanges on Grand Avenue, Regional Council members got their
first comprehensive look at the list of proposed accelerated freeway
projects during the Councils study session February 24th.
The completed list is the result of months of planning and research
conducted by MAG, with input from the cities and the Arizona Department
of Transportation (ADOT). Although now scheduled for completion
many months or years ahead of schedule, the freeway projects will
be completed in the exact same order as the current program. The
Council is expected to vote on the program for air quality conformity
analysis at its next regular meeting.
For more information, contact Eric Anderson, MAG Freeway Program
Manager, 470-1107.
Annual Report Provides Insight on Freeway Program
In 1991, a performance audit recommended that MAG become more
involved and accountable for activities surrounding the construction
of the Regional Freeway Program. MAG now provides a yearly fiscal
analysis of the Program, which examines anticipated freeway construction
projects, their projected cost, and scheduled dates of completion.
In the 1999 Annual Report on MAG Regional Freeway Program,
MAG detailed a number of major events which took place in 1998.
First was the adoption of a new material change policy. Prior
to 1998, MAG reviewed all changes to the Program, from $15,000
to $5 million. Under the new policy, MAG only looks at those projects
in which significant material changes are made.
Also in 1998, MAG became actively involved in a fair share funding analysis which looked at the ratio of taxes collected and how much comes back to Maricopa County. The analysis found that MAG was receiving only about 10.5 percent of federal and state funds distributed by the State, instead of the 35 percent it should receive under the fair share concept.
The report found that the Program has been in fiscal balance since 1992, and that construction schedules have been met. However, it also found that there have been tremendous cost increases. Construction costs alone, not including design or right-of-way costs, now average $20 million dollars per mile. Revenue has not increased, which means cash balances have been drawn down significantly, and cash flows are being watched very carefully. In the 1999 Report, MAG recommended that a system for developing better cost estimates be implemented to prevent such situations from reoccurring. MAG recommended several ways of accomplishing this, including: 1) to accelerate the 30 percent General Plan Level Design Phase; 2) to coordinate better with Environmental Processes; and 3) to mitigate design changes after General Plan completion.
MAG also recommended in the report the need for a Consolidated
State Highway Program. This program would include all State Highway
System projects and vest responsibility and authority with a single
point of contact. MAG also suggested developing long-term funding
estimates for the balance of the 20-year plan so that it may better
plan long-term freeway projects. Finally, staff recommended extending
the horizon of the Life Cycle Program to eliminate confusion between
the ADOT Life Cycle Program and the MAG Long Range Transportation
Plan. The system is to be completed within 15 years and all projects
needed to complete the Regional Freeway System should be included.
For more information, contact Eric
Anderson, MAG Freeway Program Manager, 470-1107.
Cities Accelerate Projects by Providing Own Funding
The Regional Council approved two projects brought forward by
the cities of Phoenix and Mesa for acceleration under city financing
mechanisms. The City of Phoenix will advance the completion of
the west half of the traffic interchange at the junction of I-10,
Santan and South Mountain Corridors. Using funds obtained under
a Grant Anticipation Note, the project would be completed by June
2001, rather than the originally proposed date of December 2004.
The City of Mesa proposed to advance the completion of the Gilbert
Road to Higley segment of the Red Mountain Freeway to May 2003
(from May 2005). Under this proposal, Mesa would use funding from
a Grant Anticipation Note to advance right-of-way and construction
by 24 months. Both proposals passed unanimously.
For more information, contact Eric
Anderson, MAG Freeway Program Manager, 470-1107.
Public Input Sought on Regional Domestic Violence Plan
The MAG Domestic Violence Subcommittee is finalizing draft recommendations
to be included in a Regional Domestic Violence Plan. These recommendations
will be distributed to the public in the next three weeks for
review, comment and input. MAG will be soliciting input through
a variety of methods, including direct mail and through the MAG
Web site at www.mag.maricopa.gov. During the last week of March,
the Domestic Violence Subcommittee plans to televise its meeting
on the Phoenix Channel, (Cable Channel 11), to request further
public comment and participation.
For more information, contact Carol
Kratz, MAG Human Services Manager, (602) 254-6300.
Valley Vision 2025 Members Focus on Improvement
The March 3rd meeting of the Valley Vision 2025 Committee was
postponed, to give a study group more time to look at ways to
retool the process. Over the past few months, many members of
the Committee have expressed concern about the progress of the
visioning effort. While many collaborative groups have received
exceptional input from their communities, others have met with
limited success. Two recent strategy sessions have been held to
address how to ensure the process is broad-based, representative
and credible, and that adequate resources are available. These
sessions have already produced significant results, including
consensus for a vision document model as well as ideas for redefining
the process to duplicate that model. Some exciting recommendations
are expected when the full Committee meets again April 7th.
For more information, contact Kelly
Taft, MAG Public Communications Program Manager, (602) 452-5080,
or James M. Bourey, MAG Executive Director, (602) 254-6300.
MAG to Sponsor Y2K Forum
The Maricopa Association of Governments was asked during a meeting
of City Managers to convene a forum dealing with issues surrounding
the Year 2000 computer problem. Rather than focusing only on the
technical aspects of this issue, the purpose of the forum will
be to share ideas, information, and potential actions for dealing
with the many logistical, communication and human issues involved
in addressing this problem within your communities. Any ideas
or input you have on this issue prior to this forum are appreciated.
A date has not yet been set, but expect to receive notice for
this event sometime within the next 30-45 days.
For more information, contact Kelly
Taft, MAG Public Communications Program Manager, (602) 452-5020.
Next Regional Council Meeting
The next Regional Council meeting will be held on Wednesday, March
24, 1999 at 5:00 p.m. Among the agenda items will be acceptance
of the MAG Transportation Improvement Program and Long Range Transportation
Plan for Conformity Analysis. The Clean Air Act requires that
all transportation programs be in conformance with air quality
plans. If the TIP and LRTP are approved, they would be sent on
for a conformity analysis. The programs would likely be brought
back to the Council in June for final approval. Other anticipated
agenda items are consideration and possible approval of the Accelerated
MAG Freeway Program and State Highway System; recommendations
concerning the Federal Fiscal Year 1999 MAG Federal Funds Preliminary
Closeout and potential project additions to the current federal
fiscal year; and review of public input gathered through the FY
1999 MAG Mid-Phase Public Input Opportunity Report.
For more information, contact Dennis
Smith, MAG Assistant Director, (602) 254-6300.